The master plan
Six phases. Thirty years. Honestly timed.
Planned to carry its own weight.
Energy
Its own power: solar, batteries and gas engines, with the grid as back-up.
Water
Its own treated water from protected boreholes inside the city, with a river option studied.
Food
Ofada heritage rice in the valley, greenhouses, fish ponds and a farmers' market.
Health
A health centre in every neighbourhood and a hospital with maternity and children's care.
Education
Nursery and primary schools within a walk of home; secondary schools and a vocational campus.
Jobs
Work on site: the town centre, light industry, logistics, Tech Valley, hotels, farms and city services.
Leisure
A valley park and lakes, a sports park and, if Part B comes, golf, a resort and a water park.
Faith, events & community
Multi-faith worship sites, community halls, an event centre and retreat grounds.
End-of-life care
Legacy Gardens: a memorial park with multi-faith sections and a separate perpetual-care trust.
Indicative, subject to approvals. Planned to be self-sustaining does not mean cut off, food-independent or complete on day one. Systems start small and grow with occupied homes; the city still relies on Ogun State for title, approvals and the frontage road, on the grid as back-up, and on the wider corridor for specialist hospitals and universities.
How each system is sized and timed
A plot is not yet a home. Families in fast-growing corridors often wait years for a road, find their own power, sink their own borehole and drive an hour to a good hospital. The Ridge City is planned the other way round: its own power, water and sanitation, some of its own food, its own clinics and schools, jobs on site, places to rest and gather, and a dignified place to lay its elders to rest. Each system has a site, a size, an owner and a target window.
Sized for the city at build-out
- homes at build-out (Part A ≈ 3,370)
- ≈ 7,700
- residents at build-out (range 27,000–34,000)
- ≈ 28,300
- design population the systems are sized for
- 35,000
- permanent on-site jobs at build-out
- 10,000–17,500
- occupied homes by end-2056: the conservative case we plan on
- 3,950–4,600
Capacities, not forecasts. Infrastructure is sized for a design population of 35,000. Build-out runs beyond 2056 in the planning case; the conservative 2056 case is the one we plan on.
Every system: size, first step and who delivers it
Energy
Its own power: solar, batteries and gas engines, with the grid as back-up.
- At build-out (indicative)
- About 36 MW peak at build-out; about 23 MWp of solar; 10 MW of batteries
- First step
- Interim solar-hybrid supply no earlier than 2030; mini-grid planning case 2033–2035
- Delivered by
- A licensed power partner (OGERC)
Water
Its own treated water from protected boreholes inside the city, with a river option studied.
- At build-out (indicative)
- About 13,000 m³/day of capacity; about 10,000 m³ of storage
- First step
- First boreholes and tank no earlier than 2029; planning case 2029–2031
- Delivered by
- Pertinence first; a water concessionaire after
Sanitation & waste
Its own sewage treatment with water reused on parks and farms; recycling and compost.
- At build-out (indicative)
- 8,000 m³/day of sewage treatment; about 35 tonnes of waste a day
- First step
- Sealed septic tanks until sewage module 1, planning case 2038–2041
- Delivered by
- Sewage and waste concessionaires
Food
Ofada heritage rice in the valley, greenhouses, fish ponds and a farmers' market.
- At build-out (indicative)
- About 102 acres of farms and the Agri-Hub; a share of fresh food, not all of it
- First step
- Pilot paddies and a tree nursery targeted within 2027–2029
- Delivered by
- An agri partner
Health
A health centre in every neighbourhood and a hospital with maternity and children's care.
- At build-out (indicative)
- Hospital staged to about 150 beds; 6 primary health centres
- First step
- Health centre no earlier than 2032 (planning case 2039–2041); hospital stage 1 planning case 2043–2046
- Delivered by
- A hospital operator
Education
Nursery and primary schools within a walk of home; secondary schools and a vocational campus.
- At build-out (indicative)
- 7–8 primary and 4–5 secondary schools; a tertiary or TVET campus
- First step
- First primary school no earlier than 2032; planning case 2037–2040
- Delivered by
- School operators
Jobs
Work on site: the town centre, light industry, logistics, Tech Valley, hotels, farms and city services.
- At build-out (indicative)
- About 10,000–17,500 permanent jobs at build-out
- First step
- First Ridge Works plots no earlier than 2030; planning case 2032–2035
- Delivered by
- Occupiers, operators and partner developers
Mobility
Walkable neighbourhoods, a gateway transport hub and shuttles out; trucks and visitors on their own routes.
- At build-out (indicative)
- About 26 km of spine and collector roads, 53 km of streets, a 12 km greenway
- First step
- Phase 1 gate and West Valley Drive no earlier than 2028; planning case 2029–2031
- Delivered by
- Pertinence; a state PPP is sought; a transport operator
Leisure
A valley park and lakes, a sports park and, if Part B comes, golf, a resort and a water park.
- At build-out (indicative)
- 295 acres of open space; 95 acres of sport; 38 acres of family park
- First step
- Valley protected from 2027; first greenway loop targeted within 2034–2038
- Delivered by
- Pertinence (parks); leisure operators
Faith, events & community
Multi-faith worship sites, community halls, an event centre and retreat grounds.
- At build-out (indicative)
- 16–18 worship sites; event hall for 2,000–3,000; retreat pavilion for about 5,000
- First step
- Event centre no earlier than 2032; planning case 2035–2039
- Delivered by
- Faith groups and event operators
End-of-life care
Legacy Gardens: a memorial park with multi-faith sections and a separate perpetual-care trust.
- At build-out (indicative)
- 18 acres reserved; first section 8–10 acres
- First step
- Interim arrangement with Iro targeted 2027; first section no earlier than 2033
- Delivered by
- Pertinence or a memorial-park operator
Safety
Gated access, patrols, a CCTV control room, police posts and fire stations.
- At build-out (indicative)
- 2 fire stations, 2 police posts; every home within about 5 minutes
- First step
- Security post and site office targeted within 2027
- Delivered by
- City management company; state agencies
Digital
Fibre ducts in every road reserve, and a business park on firm power.
- At build-out (indicative)
- Fibre to every plot
- First step
- Ducts laid with the first road
- Delivered by
- An internet or fibre partner
Governance
A city management company, a residents' association, a community trust and public reports.
- At build-out (indicative)
- Service charges and tariffs pay for operations and renewal, with audited accounts
- First step
- City management company and service-charge policy targeted within 2027
- Delivered by
- Pertinence, then residents and the trust
City-wide infrastructure
7 city-wide systems are planned to serve every use, each built one step ahead of the homes it serves and never all at once.
Planned
City power
Interim solar-hybrid supply, then mini-grids, then gas engines, batteries and a grid tie, added in modules as homes are occupied.
- At build-out
- About 36 MW peak at build-out
- First step
- Interim supply no earlier than 2030
Planned
Water
Protected boreholes inside the city, treatment, reservoirs and a piped network, staged one step ahead of occupied homes.
- At build-out
- About 13,000 m³/day at build-out
- First step
- First boreholes no earlier than 2029
Planned
Sewage & waste
Two enclosed modular sewage plants with treated-water reuse; a transfer station, recycling yard and compost.
- At build-out
- 8,000 m³/day sewage · 35 t/day waste
- First step
- Sewage module 1 planning case 2038–2041
Planned
Flood-resilient drainage
Homes on the ridges, the valley kept as park and flood storage, floor levels above the modelled flood plus a margin.
- At build-out
- 295 acres of valley, lakes and buffers
- First step
- Valley protected from 2027
Planned
Roads & mobility
Walkable neighbourhoods, a gateway transport hub, shuttles, and separate routes for trucks and visitors.
- At build-out
- About 26 km of spine and collector roads
- First step
- Phase 1 gate no earlier than 2028
Planned
Fibre to every plot
Ducts laid in every road reserve as it is built; an internet partner to each cluster.
- At build-out
- Fibre to every plot
- First step
- With the first road
Planned
Safety & security
Gated access, patrols, a CCTV control room, police posts and fire stations within about five minutes of every home.
- At build-out
- 2 fire stations · 2 police posts
- First step
- Security post targeted within 2027
Power, water, sewage, schools and the hospital are built and run by operators and concessionaires. Qualified partners and institutions can express interest in co-developing the city.
Indicative master plan, version 1.1 (October 2026).
Phase 1 is current. Nothing is built yet.
- Phase 1Planning
- Phase 2Not started
- Phase 3Not started
- Phase 4Not started
- Phase 5Not started
- Phase 6Not started
What has been done so far
Status: Planning · as of October 2026
Phase 1 · Foundations: in planning.
No works have started on the ground. We are evidencing the title, commissioning the studies and preparing the approvals. This tracker shows progress only when it is evidenced, so most of it is still empty, on purpose.
Of the 175 milestones in the six phases, today: 1 done, 0 committed, 0 in approval, 5 to be confirmed and 169 aspirational.
Committed means funded and contracted. Nothing is Committed yet, and we will not show it until it is.
Phase 1, the basic things in order
Provisional survey plan for Part A (OG/1089/2026/PROV.015)
28 August 2026
Done
Title evidence and counsel's title opinion in the data room
Q4 2026–Q1 2027
To be confirmed
C of O application: filing acknowledgment and reference on file
Now
To be confirmed
Phase 1A layout-approval status
Now
To be confirmed
Terms for the first release, with buyers' money protected in escrow
Q4 2026–Q1 2027
To be confirmed
Part B rights confirmed in writing
Q4 2026–2027
To be confirmed
Counsel's opinions, trustee escrow and governance adopted
Q4 2026–Q1 2027
Aspirational
Topographic survey, block flood screening and the social baseline
Q4 2026–Q2 2027
Aspirational
Survey registered and charted
Within 2027; may run into 2028
Aspirational
Community Development Agreement signed
Within 2027
Aspirational
EIA certificate
No earlier than 2028; 2028–2029
Aspirational
Master plan and Phase 1A layout approvals
2028–2029
Aspirational
Global C of O for Part A (the state sets the timing)
No earlier than 2028; 2028–2030
Aspirational
Phase 1 gate and West Valley Drive (north)
No earlier than 2028; 2029–2031
Aspirational
First serviced plots handed over
No earlier than 2029; 2030–2032
Aspirational
Six phases of five years.
Phase 1 · Now, planning2027–2031FoundationsMake the land bankable: title, trust, and one fully serviced first neighbourhood.
- Earliest window
- 2027–2031
- Planning case (the window to rely on)
- 2027–2032
Evidence and perfect the title, know the ground and the people on it, win the approvals, protect the valley, and open one complete, fully serviced first neighbourhood (Phase 1A) off West Valley Drive.
Part A · the first town
Phase 1A: one complete neighbourhood on the highest ground of the north-west ridge, reached from the Phase 1 gate. The valley, including its head at the frontage, stays park.
Part B · proposed
Rights only: an option confirmed in writing. No survey spend, marketing, sale or detailed planning.
Conservative targets · planning case at the end of 2031
- Occupied homes
- 0–20
- Residents
- 0–100
- On-site jobs
- 50–200
- Title evidenced, registered and charted; the EIA certificate and master-plan approval in hand
- The first serviced neighbourhood handed over by the end of 2032 in the planning case
- About 1.2 km of spine road, about 4 km of streets and 300–500 m³/day of water
Stretch: About 90 homes occupied by the end of 2031 and the first mini-grid in 2032. Not a forecast.
Title & approvals (13)
Provisional survey plan for Part A (OG/1089/2026/PROV.015), prepared by a SURCON-registered surveyor
Prepared 28 August 2026; on file
Done
Title evidence in a data room: the deed of assignment with its stamping and registration, the vendor's chain of title, consent status and counsel's written title opinion
Targeted within Q4 2026–Q1 2027, before any money is taken
To be confirmed
Certificate of Occupancy (C of O) application for Part A: filing acknowledgment and reference placed on file
Filing evidence now
To be confirmed
Survey lodged, registered and charted against government acquisitions, reserves and conflicting titles; root-of-title checks
Plan number targeted within 2027; may run into 2028
Aspirational · Pertinence
Topographic survey, block flood screening, hydrology, geotechnics and hydrogeology
First blocks from Q4 2026; the rest within 2027
Aspirational · Pertinence
Land-user census, social baseline and a Community Development Agreement with Iro and neighbouring communities
Targeted within 2027
Aspirational · With the community
Federal EIA, prepared to the IFC Performance Standards
Certificate no earlier than 2028; targeted within 2028–2029
Aspirational · Pertinence
Master plan approval (Ogun Ministry of Physical Planning)
Targeted within 2028–2029, after the studies
Aspirational · Pertinence
Phase 1A layout approval, with its reference published
Status to be evidenced; if not held, targeted within 2028–2029
To be confirmed
Global C of O for Part A
No earlier than 2028; targeted within 2028–2030. The state sets the timing.
Aspirational · Government or third party
Utility licences: water abstraction and the mini-grid permit (OGERC)
Targeted within 2028–2029
Aspirational · Pertinence
Title perfection for fully paid buyers: per-plot surveys, deeds and Governor's Consent in batches
No earlier than the global C of O; first filings within 12 months of it
Aspirational · Pertinence
Part B: rights confirmed in writing and an option signed
Targeted within Q4 2026–2027
To be confirmed
Infrastructure (8)
Boundary beacons, clearing, a security post, site office and patrol track
Targeted within 2027
Aspirational · Pertinence
Valley protection: no fill, dumping or building anywhere in the valley
From 2027, continuous
Aspirational · Pertinence
Phase 1 gate and junction on the Papalanto–Sagamu Road, and about 1.2 km of West Valley Drive
No earlier than 2028; targeted within 2029–2031
Aspirational · Pertinence
Phase 1A streets (about 4 km) with drains, and 0.6 km of frontage service road
No earlier than 2028; targeted within 2029–2031, block by block
Aspirational · Pertinence
Water: 2–4 protected boreholes and an elevated tank (300–500 m³/day)
No earlier than 2029; targeted within 2029–2031
Aspirational · Pertinence
Power: an interim solar-hybrid supply sized to occupied homes, growing into a 0.5–1 MWp mini-grid
Interim no earlier than 2030; mini-grid planning case 2033–2035
Aspirational · Partner-led
Security edge: the west frontage and Phase 1A fenced (about 3 km); solar street lighting on the spine
Targeted within 2029–2031
Aspirational · Pertinence
Sanitation: approved sealed septic tanks emptied by licensed tankers, until the first sewage plant
From the first occupation
Aspirational · Pertinence
Releases (4)
The first serviced neighbourhood (Phase 1A). Plots are allocated only on the approved layout; release terms and money protection are being confirmed
Allocation only after the Phase 1A layout approval: planning case 2029–2030
To be confirmed
Serviced handover, block by block: road access, drains and a water point, then power when the interim supply opens, verified by an independent quantity surveyor
No earlier than 2029; targeted within 2030–2032
Aspirational · Pertinence
First frontage commercial plots, on their own service road
No earlier than 2029; targeted within 2031–2034
Aspirational · Pertinence
First Ridge Works plots, sold with build-start covenants; an anchor parcel held for an anchor
No earlier than 2030; targeted within 2032–2035
Aspirational · Partner-led
Community & services (3)
Community liaison office and benefit plan: local hiring, apprenticeships and scholarships
Targeted within 2027–2028
Aspirational · With the community
First-aid post and an ambulance arrangement to the nearest hospital
From the first works
Aspirational · Pertinence
A neighbourhood park and the first section of the valley greenway beside Phase 1A
Targeted within 2030–2032
Aspirational · Pertinence
Partner projects (6)
Ofada heritage rice paddies and a tree nursery: the first visible activity on site
Pilot targeted within 2027–2029, once hydrology confirms the paddy areas
Aspirational · Partner-led
A power partner for the interim supply and the first mini-grid
Agreement targeted within 2027–2028
Aspirational · Partner-led
Memoranda of understanding (not buildings yet) with a hospital operator, a school operator, an event operator and a water concessionaire
Targeted within 2027–2029
Aspirational · Partner-led
A Ridge Works anchor occupier (agro-processing or light manufacturing)
Targeted within 2028–2031
Aspirational · Partner-led
A show village of model homes in Phase 1A
No earlier than 2030; targeted within 2031–2032
Aspirational · Partner-led
Fuel, CNG and EV charging at the north-east junction
No earlier than 2030; targeted within 2031–2034
Aspirational · Partner-led
Gates to open Phase 2 · all must be true
- The global C of O for Part A granted, with any land under acquisition held back on a documented route.
- The EIA certificate held; the master plan and the Phase 2 layout approved.
- The first neighbourhood serviced and handed over, verified by an independent quantity surveyor, with no buyer past their contracted handover window.
- Phase 2 passes its funding test: an independent cost plan shows its committed sources cover its costs, with buyers' receipts held in escrow.
- A power partner contracted and the OGERC licensing route confirmed.
- The city management company operating, with its service-charge accounts published.
- The host-community agreement in force and no unresolved claim on Phase 2 land.
Phase 22032–2036First LightMake it liveable: serviced releases, the first schools, city utilities as demand arrives, and the town centre.
- Earliest window
- 2032–2036
- Planning case (the window to rely on)
- Opens 2032–2033; runs to 2039–2041
Serviced releases continue block by block. Valley Boulevard and Ridge Central begin when their anchors are in sight. Utilities, schools and a health centre open as occupied homes reach their triggers. Operators may choose to come earlier.
Part A · the first town
Phase 1B, Ridge Heights, the west neighbourhood centre, the main gateway, Valley Boulevard to Ridge Central and the health campus, staff homes and terraces, the event centre and the utilities campus.
Part B · proposed
If an option is in force: survey, charting, root of title and the C of O application. Nothing is marketed or sold.
Conservative targets · planning case at the end of 2036
- Occupied homes
- 250–500
- Residents
- 900–1,900
- On-site jobs
- 200–750
- Phase 1B handed over; Ridge Heights being serviced
- About 1,000 m³/day of water and a mini-grid of about 1 MWp; sealed septic tanks still in use
- The first primary school and Ridge Central stage 1 under way with operators
Stretch: About 1,300 homes occupied by the end of 2036, with power module 1 and the health centre in 2036. Not a forecast.
Title & approvals (6)
Governor's Consent for fully paid plots, in batches, so that mortgages can be registered
Continuous from the C of O; 2032–2038
Aspirational · Pertinence
Phase 2 layout approvals: Phase 1B, Ridge Heights, the neighbourhood centres and Ridge Central
Targeted within 2031–2033
Aspirational · Pertinence
Power licensing for city power module 1 (OGERC) and a gas-supply agreement (NMDPRA)
Targeted within 2036–2039
Aspirational · Partner-led
Legacy Gardens approval by Obafemi-Owode Local Government at the chosen site
Targeted within 2032–2035
Aspirational · Government or third party
The first environmental audit and the first five-year master-plan review, adopted publicly
Targeted within 2032–2034
Aspirational · Pertinence
Part B, only under a signed option: survey, charting, root of title and the C of O application
No earlier than 2032; targeted within 2032–2036
Aspirational · Pertinence
Infrastructure (8)
West Valley Drive south, the first collector roads and local streets, block by block
No earlier than 2032; targeted within 2033–2038
Aspirational · Pertinence
Valley Boulevard section 1 (about 1.8 km) to Ridge Central and the health campus
No earlier than 2034; targeted within 2035–2038
Aspirational · Pertinence
The main gateway and junction east of the valley head
No earlier than 2033; targeted within 2035–2038
Aspirational · Pertinence
The full Part A perimeter and a CCTV control room
Targeted within 2033–2036
Aspirational · Pertinence
Water stage 1: treatment, storage and a piped network (1,000–1,500 m³/day)
Targeted within 2034–2038, one step ahead of occupied homes
Aspirational · Partner-led
City power module 1 (about 3–5 MW firm)
No earlier than 2033; planning case 2039–2041, at about 1,000 occupied homes
Aspirational · Partner-led
Sewage module 1 (500 m³/day)
No earlier than 2032; planning case 2038–2041, at about 800 homes in one catchment
Aspirational · Partner-led
The valley greenway's first loop (2–4 km)
Targeted within 2034–2038
Aspirational · Pertinence
Releases (5)
Later serviced releases: Phase 1B (Ridge Courts West, Ridge Gardens near the west centre, the lakeside Homecoming Enclave)
Handover planning case 2032–2035
Aspirational · Pertinence
Ridge Heights, on the south-west high ground
Handover no earlier than 2032; planning case 2034–2037
Aspirational · Pertinence
Land for partner-built terraces and staff and affordable homes
Released no earlier than 2032; first completions planning case 2034–2036
Aspirational · Partner-led
Ridge Central parcels around the developer-held core
No earlier than 2034; targeted within 2036–2039
Aspirational · Pertinence
Sites leased to operators: the health campus, schools and the event centre; worship sites under a published policy
As each operator signs; 2034–2039
Aspirational · Partner-led
Community & services (5)
First nursery and primary school
No earlier than 2032; planning case 2037–2040, at about 600 occupied homes
Aspirational · Partner-led
24-hour health centre with maternity
No earlier than 2032; planning case 2039–2041, at about 1,000 occupied homes
Aspirational · Partner-led
Community hall, the first worship sites and the community sports park, stage 1
Targeted within 2035–2039
Aspirational · Pertinence
Police post and fire station 1
Targeted within 2035–2039
Aspirational · Government or third party
Legacy Gardens, first section (multi-faith, including same-day burial)
No earlier than 2033; targeted within 2034–2037
Aspirational · Pertinence
Partner projects (6)
Gateway event centre (a hall for about 2,000–3,000 guests)
No earlier than 2032; targeted within 2035–2039
Aspirational · Partner-led
Ridge Central stage 1: market, supermarket, banks, offices and the civic plaza
No earlier than 2034; targeted within 2036–2039
Aspirational · Partner-led
Water and sewage concession for Part A
Contract targeted within 2033–2036
Aspirational · Partner-led
Gateway transport hub and scheduled shuttles
Targeted within 2036–2039
Aspirational · Partner-led
Partner-built terraces and staff homes
2033–2040
Aspirational · Partner-led
A filling station on the east road for trucks
2034–2039
Aspirational · Partner-led
Gates to open Phase 3 · all must be true
- Phase 2 trunk works at least 80% complete, verified by the independent quantity surveyor.
- Water and power operating, with tariffs or service charges published and audited; sewage module 1 operating or contracted.
- About 1,000 occupied homes, or equivalent anchor demand.
- At least two anchors operating: the first primary school, and the health centre or Ridge Central stage 1.
- The Phase 3 layout approved and Phase 3's funding test passed.
- A residents' association constituted and the first environmental audit passed.
Phase 32037–2041The Complete TownMake it complete: all of Part A's trunk infrastructure.
- Earliest window
- 2037–2041
- Planning case (the window to rely on)
- Opens 2039–2041; Part A trunk complete 2044–2047
All of Part A's main roads, drains, power ring, water mains and sewers are completed: no earlier than the end of 2041, and in the planning case in 2044–2047. Part A becomes a working town of its own, whether or not Part B follows.
Part A · the first town
Completion: Valley Boulevard section 2, Ridge Gardens and Courts East, apartments, the Golden Years cluster, the gateway hotel, Tech Valley, the Agri-Hub core, the secondary school, hospital stage 1, Legacy Gardens and the valley park.
Part B · proposed
C of O, EIA, master plan and first layout approval; the leisure parkway agreed with the state. No Part B parcel is serviced before every approval is in hand.
Conservative targets · planning case at the end of 2041
- Occupied homes
- 1,250–1,700
- Residents
- 4,700–6,500
- On-site jobs
- 1,100–2,550
- About 5 MW of firm power, 3,000 m³/day of water and 2,000 m³/day of sewage treatment
- Primary school, health centre and Ridge Central stage 1 operating
- Part A trunk completion targeted for 2044–2047
Stretch: About 2,850 homes occupied by the end of 2041 and Part A's trunk complete by end-2041. Not a forecast.
Title & approvals (4)
Part B global C of O (only if Part B is secured)
No earlier than 2034; targeted within 2035–2039. The state sets the timing.
Aspirational · Government or third party
Part B EIA, master plan and first layout approval; the leisure parkway agreed with Ogun State and the LGA
Targeted within 2039–2044
Aspirational · Pertinence
Power licence upgrade (OGERC) and a grid-connection application
Targeted within 2041–2045
Aspirational · Partner-led
Buyers' title perfection substantially complete for the first releases
Targeted by 2043
Aspirational · Pertinence
Infrastructure (6)
All of Part A's trunk: Valley Boulevard section 2, collectors, storm drainage, the 33 kV ring, water mains and sewers
No earlier than end-2041; planning case 2044–2047
Aspirational · Pertinence
Cross-valley links, built as bridges or open causeways that let floodwater pass
Targeted within 2041–2045
Aspirational · Pertinence
Power module 2 and the Part A solar plant complete
Targeted within 2041–2046
Aspirational · Partner-led
Water stage 2, and sewage module 2 with treated water reused on parks and farms
Targeted within 2040–2046
Aspirational · Partner-led
The valley park complete, with the greenway loop around Part A
Targeted within 2040–2046
Aspirational · Pertinence
Recycling and compost yards; fire station 2
2040–2046
Aspirational · Partner-led
Releases (4)
Ridge Gardens East and Ridge Courts East, sold as serviced releases
Handover targeted within 2038–2042
Aspirational · Pertinence
Apartments near Ridge Central and the Golden Years cluster beside the health campus
Targeted within 2041–2046
Aspirational · Partner-led
Sites for the gateway hotel and Ridge Tech Valley
No earlier than 2037; targeted within 2040–2044
Aspirational · Partner-led
The Agri-Hub core and the rest of the Part A paddies
2039–2045
Aspirational · Partner-led
Community & services (4)
Hospital stage 1 (about 50 beds, with maternity and children's care)
No earlier than 2035; planning case 2043–2046, at about 2,000 occupied homes
Aspirational · Partner-led
First secondary school, then more primary schools as enrolment grows
No earlier than 2034; planning case 2041–2044, at about 1,500 occupied homes
Aspirational · Partner-led
Library and community centre in Ridge Central; a clinic in each neighbourhood centre
2040–2046
Aspirational · Pertinence
A second police post and fire station
2041–2046
Aspirational · Government or third party
Partner projects (4)
Gateway hotel and serviced apartments (about 100–120 keys)
No earlier than 2037; targeted within 2040–2044, once event demand is proven
Aspirational · Partner-led
Ridge Tech Valley: offices, co-working and BPO on firm power and fibre
No earlier than 2037; targeted within 2041–2045
Aspirational · Partner-led
Agri-Hub stage 2: greenhouses, aquaculture, a training centre and the farmers' market
2039–2045
Aspirational · Partner-led
Hospital stage 1, with development-finance support where it qualifies
Planning case 2043–2046
Aspirational · Partner-led
Gates to open Phase 4 · all must be true
- Part A trunk infrastructure at least 80% complete, on a funded path to completion and verified by the independent quantity surveyor.
- Part B's C of O, EIA and first layout approval in hand before any Part B sale or servicing.
- The leisure parkway agreed with Ogun State and the LGA.
- At least one destination operator signed, with its own financing, before land is serviced for it.
- At least 5 MW of firm power and 3,000 m³/day of water operating, with three years of audited accounts.
- Phase 4's funding test passed.
Phase 42042–2046The Destination CityMake it a destination: Part B and the leisure parkway.
- Earliest window
- 2042–2046
- Planning case (the window to rely on)
- Opens 2044–2047; first destination operator trading 2046–2050
With Part B titled and operators signed, the resort, golf course, retreat and convention grounds, amusement and water park, sports complex and a tertiary campus open on their own leisure parkway. None opens before 2042; in the planning case the first destination operator trades in 2046–2050.
Part A · the first town
Infill, homes near Ridge Central, and the hospital's growth.
Part B · proposed
The leisure parkway, Part B's first trunk works, the destination uses, the first Part B neighbourhoods, the district centre and Part B utilities.
Conservative targets · planning case at the end of 2046
- Occupied homes
- 2,300–2,700
- Residents
- 8,700–10,200
- On-site jobs
- 2,050–4,050
- About 12 MW of firm power, 5,000 m³/day of water and 3,000 m³/day of sewage treatment
- The first destination operator trading in 2046–2050 in the planning case
Stretch: About 4,000 homes occupied by the end of 2046 and destination uses from 2042–2044. Not a forecast.
Title & approvals (3)
Part B layout approvals stage by stage; operators' permits; event-day traffic plans agreed with the state and LGA
2044–2050
Aspirational · Pertinence
Water licence for Part B and the discharge permit for sewage plant B
Targeted within 2045–2050
Aspirational · Pertinence
Master plan review 3, adopted publicly
2042–2043
Aspirational · Pertinence
Infrastructure (4)
The leisure parkway: the east road upgraded and extended, with a visitor park-and-ride
No earlier than 2042; targeted within 2045–2049
Aspirational · Government or third party
Part B collectors and local streets for the first neighbourhoods
2045–2051
Aspirational · Pertinence
Part B utilities: solar plant B, substation, water works and sewage plant
Targeted within 2046–2051
Aspirational · Partner-led
Ridge Lake as flood storage; the Part B perimeter and gates
2045–2051
Aspirational · Pertinence
Releases (3)
Destination sites on long lease or joint venture, each only after its operator signs
No earlier than 2042; targeted within 2045–2050
Aspirational · Partner-led
Part B neighbourhoods 1 and 2
No earlier than 2042; targeted within 2046–2051
Aspirational · Pertinence
Part B district centre and health satellite
Targeted within 2047–2051
Aspirational · Partner-led
Community & services (3)
Hospital toward about 100, then 150 beds; the Part B health satellite
No earlier than 2043; targeted within 2047–2052
Aspirational · Partner-led
Part B schools, and a tertiary or vocational campus
No earlier than 2042; targeted within 2047–2052
Aspirational · Partner-led
Fire and police cover for Part B
2047–2052
Aspirational · Government or third party
Partner projects (5)
Lakeside wellness resort and spa (about 100–150 keys)
No earlier than 2042; targeted within 2046–2050
Aspirational · Partner-led
9-hole golf course, driving range and academy
No earlier than 2042; targeted within 2046–2050
Aspirational · Partner-led
Retreat and convention grounds with a convention hotel and lodges
No earlier than 2042; targeted within 2046–2050
Aspirational · Partner-led
Family amusement and water park
No earlier than 2042; targeted within 2046–2050
Aspirational · Partner-led
Regional sports complex and academy
No earlier than 2043; targeted within 2047–2051
Aspirational · Partner-led
Gates to open Phase 5 · all must be true
- The leisure parkway open and at least two destination operators trading.
- An event-day traffic management plan approved and tested.
- Part B trunk infrastructure at least 50% complete, verified by the independent quantity surveyor.
- Master plan review 3 adopted and Phase 5's funding test passed.
Phase 52047–2051MaturityMake it mature: full systems and the golden years.
- Earliest window
- 2047–2051
- Planning case (the window to rely on)
- Opens 2050–2053; Part B trunk complete 2056–2060
Part B's trunk infrastructure is completed (no earlier than the end of 2051; planning case 2056–2060), and city systems grow toward build-out capacity, sized for a design population of 35,000.
Part A · the first town
Renewal and, where demand supports it, more homes near the centres.
Part B · proposed
Trunk completion, apartments, Golden Years Village B, Tech Valley B and agro-processing.
Conservative targets · planning case at the end of 2051
- Occupied homes
- 2,900–3,400
- Residents
- 11,100–12,900
- On-site jobs
- 2,600–5,100
- About 12 MW of firm power, 8,000 m³/day of water and 4,000 m³/day of sewage treatment
- Part B trunk under way; completion targeted for 2056–2060
Stretch: About 5,850 homes occupied by the end of 2051. Not a forecast.
Title & approvals (2)
Master plan review 4 and licence renewals
2047–2048
Aspirational · Pertinence
A Legacy Gardens extension in Part B, only if demand needs it, under the same siting tests
No earlier than 2047
Aspirational · Government or third party
Infrastructure (3)
Part B trunk infrastructure complete: spine, collectors, storm drainage and sewers
No earlier than end-2051; planning case 2056–2060
Aspirational · Pertinence
Power, water and sewage grow toward build-out; the first battery replacement cycle
2050–2056
Aspirational · Partner-led
Waste transfer at full capacity
2050–2056
Aspirational · Partner-led
Releases (2)
Apartments B, Golden Years Village B, Tech Valley B and the agro-processing cluster
No earlier than 2047; targeted within 2050–2056
Aspirational · Partner-led
The remaining Part B neighbourhoods
2050–2056
Aspirational · Pertinence
Community & services (3)
Hospital at about 150 beds if demand supports it; six primary health centres city-wide
2050–2056
Aspirational · Partner-led
Schools toward 7–8 primary and 4–5 secondary
2050–2056
Aspirational · Partner-led
Assisted living and day care for older residents
2050–2056
Aspirational · Partner-led
Partner projects (2)
Golden Years Village B: independent and assisted living
No earlier than 2047; targeted within 2050–2056
Aspirational · Partner-led
Ridge Tech Valley B and the agro-processing cluster
No earlier than 2047; targeted within 2050–2056
Aspirational · Partner-led
Gates to open Phase 6 · all must be true
- Part B trunk infrastructure handed over to the city management company and verified by the independent quantity surveyor.
- Master plan review 4 adopted.
- The Ridge City Community Trust endowed from land proceeds; the memorial park's perpetual-care trust audited and separate.
- An asset-renewal plan funded from service charges and tariffs.
Phase 62052–2056LegacyMake it last: build-out, renewal and stewardship.
- Earliest window
- 2052–2056
- Planning case (the window to rely on)
- Opens 2055–2060; build-out runs beyond 2056
Infill and the final releases, repowering of the first solar plants, and the hand-over of the valley, the greenways and the community assets to a community trust. Build-out (about 7,700 homes) runs beyond 2056 in the planning case.
Part A · the first town
Renewal and infill near the centres if demand supports it.
Part B · proposed
The final neighbourhoods, and a public decision on the strategic reserve.
Conservative targets · planning case at the end of 2056
- Occupied homes
- 3,950–4,600
- Residents
- 15,000–17,500
- On-site jobs
- 3,550–6,900
- About 20 MW of firm power, 10,000 m³/day of water and 5,000 m³/day of sewage treatment
- Community assets handed to the trust; build-out continues beyond 2056
Stretch: About 7,100 homes occupied by the end of 2056. Not a forecast.
Title & approvals (2)
Master plan review 5 and the strategic-reserve decision
No earlier than 2052
Aspirational · Pertinence
The Ridge City Community Trust registered and funded
Targeted within 2052–2056
Aspirational · With the community
Infrastructure (4)
Local streets complete
2055–2060
Aspirational · Pertinence
Power at build-out, with the first-generation solar repowered
2055–2060
Aspirational · Partner-led
Water and sewage at build-out
2055–2060
Aspirational · Partner-led
Road resurfacing and plant renewal paid from the renewal reserves
2055–2060
Aspirational · Pertinence
Releases (2)
The remaining infill plots and parcels
2055–2060
Aspirational · Pertinence
The strategic reserve: a second golf nine, a campus expansion, a transit link or a data centre, decided publicly
No earlier than 2052
Aspirational · Pertinence
Community & services (1)
Full provision for the design population: schools, up to about 150 hospital beds, six health centres and two fire stations
At build-out; beyond 2056 in the planning case
Aspirational · Partner-led
Partner projects (2)
Apartments near Ridge Central and the Part B district centre, if demand supports them
No earlier than 2052
Aspirational · Partner-led
A strategic-reserve project chosen at review
No earlier than 2052
Aspirational · Partner-led
Hand-over conditions · all must be true
- The community trust endowed and governed, with residents represented.
- The perpetual-care trust separate and audited.
- Renewal reserves funded from service charges and tariffs.
- Residents on the city management company's board.
Indicative, subject to approvals. Every date is a target window, never a promise.
What the status labels mean
- Done
- Completed, with the evidence on file.
- Committed
- Funded and contracted. Nothing carries this label yet.
- In approval
- An application is lodged and its reference is on file; a public body controls the outcome and timing.
- To be confirmed
- The facts must be evidenced in writing before the item is relied on.
- Aspirational
- Planned, but not yet funded and contracted.
How we set target windows
Every comparable new city in Africa delivered more slowly than first announced. So every date here is a target window with its conditions, set from a conservative model of how fast owners actually build, and never a promise.
No earlier than
The earliest year a milestone could happen. A phase cannot open before its 5-year window.
Planning case
The conservative window we plan and fund against, derived from the occupancy model and the gates. This is the one to rely on.
Stretch
What could happen if approvals, sales and partners move faster. Shown for completeness; not a forecast.
The rules this plan follows
- A phase opens when its gates are met, including a funding test, not when the calendar says so.
- Facilities open on evidence: each has a demand trigger (occupied homes or an operator's own case), plus about a year to build.
- Committed means funded and contracted. Anything that needs an operator, utility or financier is Aspirational until it signs.
- We sell only what can be serviced, and plots are allocated only on an approved layout.
- Buyers' money is held in escrow and released against certified works (proposed, to be adopted before any money is taken).
- If a gate slips, the next phase slips, and we say so publicly within 14 days, with the reason and a new window.
- Unbuilt infrastructure is never priced into a plot.
Our planning case assumes owner-builders build slowly: about a quarter of a year's handed-over plots occupied four years later, and about half after nine. On that basis the city reaches about 1,000 occupied homes in 2039–2041, and every facility that waits for that threshold is placed there, not earlier.
Facilities open on evidence, not on hope
| Facility | Opens when | No earlier than | Planning case |
|---|---|---|---|
| First solar-hybrid mini-grid (0.5–1 MWp) | About 100 occupied homes, or an industrial anchor | 2030 | 2033–2035 |
| First nursery and primary school | About 600 occupied homes, or an operator's own enrolment case | 2032 | 2037–2040 |
| Sewage module 1 (500 m³/day) | About 800 occupied homes in one catchment | 2032 | 2038–2041 |
| 24-hour health centre with maternity | About 1,000 occupied homes, or an operator's own case | 2032 | 2039–2041 |
| City power module 1 (about 3 MW firm) | About 1,000 occupied homes, or an anchor needing more than 1 MW | 2033 | 2039–2041 |
| First secondary school | About 1,500 occupied homes, or an operator's own case | 2034 | 2041–2044 |
| Hospital stage 1 (about 50 beds) | About 2,000 occupied homes, or a wider-catchment case | 2035 | 2043–2046 |
| Gateway hotel | Event bookings and corridor demand proven by the operator | 2037 | 2040–2044 |
| Resort, golf, water park, retreat grounds | An operator signed with its own financing; Part B titled | 2042 | 2046–2050 |
Each window includes about a year to build after the trigger is met. Operators are welcome to come earlier on their own business case; the plan never assumes it.
What comparable new cities teach
Alaro City, Lagos
About seven years from conception to groundbreaking, even with the state as a partner. Plots were sold after the C of O and master plan.
Tatu City, Kenya
First homes launched in 2015 and phased over 20 years; about ten years from launch to a functioning town (company-reported).
Lekki Free Zone, Lagos
Incorporated in 2006; its big anchors arrived about 17 years later. Anchor-driven cities have long gestation.
Sources
- Alaro City, Lagos: ThisDay, 2019 (opens in a new tab)
- Tatu City, Kenya: Tatu City, 2025 (opens in a new tab)
- Lekki Free Zone, Lagos: Wikipedia (opens in a new tab)
Cited for their timelines only. The Ridge City is independent of these projects and implies no endorsement.
Title and approvals, in order
Before a plot can be sold under a binding contract, the land needs evidenced title, a registered and charted survey, a counted and consulted community, flood-screened blocks and the layout approval. Before it can be handed over, it needs the EIA and the works. Most of these steps are in the hands of state and federal agencies.
Title status today
Deed of assignment in place; provisional survey plan (OG/1089/2026/PROV.015) for Part A completed by a SURCON-registered surveyor; Certificate of Occupancy (C of O) application in process.
Step 1: Title evidence and counsel's opinions
Counsel; Ogun Lands Registry
The deed of assignment (parties, date, stamping, registration), the vendor's chain of title, consent status and a written title opinion, placed in a data room.
Q4 2026–Q1 2027, before any money is taken
To be confirmed
Step 2: Register and chart the survey
Ogun Surveyor-General; Bureau of Lands
Lodge the provisional plan, obtain a registered plan number and chart it against acquisitions, reserves and conflicting titles.
3–9 months; targeted within 2027
Aspirational
Step 3: Root of title and acquisition check
Bureau of Lands; Land Use Act
Confirm the land is not under government acquisition; if any is, hold it back and follow an excision or ratification route.
6–18 months, in parallel
Aspirational
Step 4: Know the ground and the people on it
Within the EIA scope
Topographic survey, block flood screening, hydrology, hydrogeology and a land-user census and social baseline, before any binding sale.
First blocks from Q4 2026; full studies within 2027
Aspirational
Step 5: Federal EIA
Federal Ministry of Environment (EIA Act)
Scoping, baseline studies, a 21-day public display and hearing, then the certificate; prepared to the IFC Performance Standards.
12–24 months; certificate no earlier than 2028, targeted 2028–2029
Aspirational
Step 6: Master plan and Phase 1A layout approval
Ogun Ministry of Physical Planning (2025 regulations)
Approve the indicative master plan and a phased layout. No plot is allocated or pegged before the layout approval.
6–18 months; targeted 2028–2029
To be confirmed
Step 7: Global Certificate of Occupancy
Ogun Bureau of Lands (OLARMS)
The C of O for Part A follows survey registration and a clean root of title. The state controls the timing.
No earlier than 2028; targeted 2028–2030
Aspirational
Step 8: Governor's Consent for buyers
Land Use Act s.22
Per-plot surveys, deeds and consent in batches, once the C of O exists. Mortgages can be registered only after consent.
6–12 months per batch, after the C of O
Aspirational
Step 9: Utility and operator licences
OGERC, NMDPRA, NIWRMC, Ministry of Health, Local Government
Power, gas, water abstraction, hospital registration, filling stations and the memorial park, each before its facility opens.
As each facility approaches its trigger
Aspirational
Step 10: All major infrastructure
Pertinence, concessionaires and the state
All of Part A's main roads, drains, power ring, water mains and sewers.
No earlier than end-2041; planning case 2044–2047
Aspirational
When will all major infrastructure be built?
- Part A
- No earlier than end-2041; planning case 2044–2047
- Part B (only if secured and titled)
- No earlier than end-2051; planning case 2056–2060
- Build-out (about 7,700 homes)
- Beyond 2056 in the planning case
These are targets. The schedule is driven by approvals, sales, partners and funding tests; most title steps are controlled by state and federal agencies, and we never imply a C of O date.
Infrastructure by phase
Cumulative at the end of each phase’s earliest window. The large figure is the planning case; the small one in brackets is the stretch case, which is not a forecast. Utilities are sized to occupied homes, never to plots sold.
| System (cumulative) | P1End-2031 | P2End-2036 | P3End-2041 | P4End-2046 | P5End-2051 | P6End-2056 |
|---|---|---|---|---|---|---|
| Spine roads (km)About 12.5 km at build-out (West Valley Drive, Valley Boulevard, leisure parkway) | 1 | 2(4) | 4(6) | 6(10) | 8(13) | 10(13) |
| Other collector roads (km)About 13.5 km at build-out | 0 | 0(2) | 2(5) | 5(7) | 7(12) | 12(14) |
| Local streets (km)About 53 km at build-out, the rest inside partner parcels | 5(8) | 11(13) | 17(22) | 22(28) | 28(40) | 40(47) |
| Valley greenway (km)About 12 km at build-out | 0(1) | 3 | 3(8) | 8(10) | 10(12) | 12 |
| Firm power (MW)Module 1 at about 1,000 occupied homes; about 36 MW peak at build-out | 0 | 0(8) | 5(12) | 12(20) | 12(25) | 20(35) |
| Solar (MWp)Ground-mounted, rooftop and a floating option | 0(1) | 1(8) | 8(9) | 9(18) | 17(20) | 18(21) |
| Water production (m³/day)One step ahead of occupied homes; 13,000 m³/day at build-out | 300 | 1,000(3,000) | 3,000(8,000) | 5,000(10,000) | 8,000(13,000) | 10,000(13,000) |
| Sewage treatment (m³/day)Sealed septic tanks until module 1; 8,000 m³/day at build-out | 0 | 0(2,000) | 2,000(4,000) | 3,000(5,000) | 4,000(8,000) | 5,000(8,000) |
| Occupied homes (homes)The occupancy model; about 7,700 homes at build-out | 0(90) | 250(1,300) | 1,250(2,850) | 2,300(4,000) | 2,900(5,850) | 3,950(7,100) |
Risks we manage
The risks that matter most here, and how the plan is built to absorb them.
Title and approvals take longer than the windows.
Conservative windows taken from comparable cities; works start on gates, not dates; a title update every 30 days until the C of O is granted.
Title evidence turns out weaker than stated, or charting finds land under acquisition.
Evidence before any money is taken; the exact title wording everywhere; charting before any binding contract; affected land held back from sale.
The valley is wetter or larger than the desk study suggests.
Hydrology first; homes on flood-screened high ground only; floor levels above the modelled flood; a relocation-or-refund clause in every contract.
Buyers wait longer than their contracts say.
We sell only what can be serviced; handover windows and long-stop dates in contracts; no allocation before the layout approval.
Anchors such as a hospital or schools do not come when planned.
Operators courted from 2027; published demand triggers; long leases on anchor terms; smaller interim facilities first.
Land sales alone do not pay for all of the infrastructure.
We say so openly. Each phase must pass an independent funding test before it opens; utilities are concession-financed; partners are sought for the rest.
Gas supply or power licensing is delayed.
Solar and batteries first, trucked gas as a bridge, the OGERC route confirmed early, and the grid treated as an upside, never a dependency.
People farm, live on or hold sacred sites on the land; community disputes.
A land-user census now, a livelihood-restoration framework, a heritage protocol and a Community Development Agreement before works.
Part B is not secured, not next to Part A, or priced up by hold-outs.
Part A is planned as a complete town on its own; Part B is never marketed or sold before it is titled.
Naira cost inflation.
A 30–50% contingency in the cost plan, imported equipment carried by partners, and an annual re-baseline of costs.

Build it with us