Artist's impression: a hand pointing at a scale model of a planned town of white houses, trees and a lake

The master plan

Six phases. Thirty years. Honestly timed.

Built one serviced neighbourhood at a time, and promised only as fast as the evidence allows.

Planned to carry its own weight.

Its own power, water and sanitation, its own clinics and schools, and jobs on site. Each system has a site, a size, an owner and a target window.
  • Energy

    Its own power: solar, batteries and gas engines, with the grid as back-up.

  • Water

    Its own treated water from protected boreholes inside the city, with a river option studied.

  • Food

    Ofada heritage rice in the valley, greenhouses, fish ponds and a farmers' market.

  • Health

    A health centre in every neighbourhood and a hospital with maternity and children's care.

  • Education

    Nursery and primary schools within a walk of home; secondary schools and a vocational campus.

  • Jobs

    Work on site: the town centre, light industry, logistics, Tech Valley, hotels, farms and city services.

  • Leisure

    A valley park and lakes, a sports park and, if Part B comes, golf, a resort and a water park.

  • Faith, events & community

    Multi-faith worship sites, community halls, an event centre and retreat grounds.

  • End-of-life care

    Legacy Gardens: a memorial park with multi-faith sections and a separate perpetual-care trust.

Indicative, subject to approvals. Planned to be self-sustaining does not mean cut off, food-independent or complete on day one. Systems start small and grow with occupied homes; the city still relies on Ogun State for title, approvals and the frontage road, on the grid as back-up, and on the wider corridor for specialist hospitals and universities.

How each system is sized and timed

A plot is not yet a home. Families in fast-growing corridors often wait years for a road, find their own power, sink their own borehole and drive an hour to a good hospital. The Ridge City is planned the other way round: its own power, water and sanitation, some of its own food, its own clinics and schools, jobs on site, places to rest and gather, and a dignified place to lay its elders to rest. Each system has a site, a size, an owner and a target window.

Sized for the city at build-out

homes at build-out (Part A ≈ 3,370)
≈ 7,700
residents at build-out (range 27,000–34,000)
≈ 28,300
design population the systems are sized for
35,000
permanent on-site jobs at build-out
10,000–17,500
occupied homes by end-2056: the conservative case we plan on
3,950–4,600

Capacities, not forecasts. Infrastructure is sized for a design population of 35,000. Build-out runs beyond 2056 in the planning case; the conservative 2056 case is the one we plan on.

Every system: size, first step and who delivers it

  • Energy

    Its own power: solar, batteries and gas engines, with the grid as back-up.

    At build-out (indicative)
    About 36 MW peak at build-out; about 23 MWp of solar; 10 MW of batteries
    First step
    Interim solar-hybrid supply no earlier than 2030; mini-grid planning case 2033–2035
    Delivered by
    A licensed power partner (OGERC)
  • Water

    Its own treated water from protected boreholes inside the city, with a river option studied.

    At build-out (indicative)
    About 13,000 m³/day of capacity; about 10,000 m³ of storage
    First step
    First boreholes and tank no earlier than 2029; planning case 2029–2031
    Delivered by
    Pertinence first; a water concessionaire after
  • Sanitation & waste

    Its own sewage treatment with water reused on parks and farms; recycling and compost.

    At build-out (indicative)
    8,000 m³/day of sewage treatment; about 35 tonnes of waste a day
    First step
    Sealed septic tanks until sewage module 1, planning case 2038–2041
    Delivered by
    Sewage and waste concessionaires
  • Food

    Ofada heritage rice in the valley, greenhouses, fish ponds and a farmers' market.

    At build-out (indicative)
    About 102 acres of farms and the Agri-Hub; a share of fresh food, not all of it
    First step
    Pilot paddies and a tree nursery targeted within 2027–2029
    Delivered by
    An agri partner
  • Health

    A health centre in every neighbourhood and a hospital with maternity and children's care.

    At build-out (indicative)
    Hospital staged to about 150 beds; 6 primary health centres
    First step
    Health centre no earlier than 2032 (planning case 2039–2041); hospital stage 1 planning case 2043–2046
    Delivered by
    A hospital operator
  • Education

    Nursery and primary schools within a walk of home; secondary schools and a vocational campus.

    At build-out (indicative)
    7–8 primary and 4–5 secondary schools; a tertiary or TVET campus
    First step
    First primary school no earlier than 2032; planning case 2037–2040
    Delivered by
    School operators
  • Jobs

    Work on site: the town centre, light industry, logistics, Tech Valley, hotels, farms and city services.

    At build-out (indicative)
    About 10,000–17,500 permanent jobs at build-out
    First step
    First Ridge Works plots no earlier than 2030; planning case 2032–2035
    Delivered by
    Occupiers, operators and partner developers
  • Mobility

    Walkable neighbourhoods, a gateway transport hub and shuttles out; trucks and visitors on their own routes.

    At build-out (indicative)
    About 26 km of spine and collector roads, 53 km of streets, a 12 km greenway
    First step
    Phase 1 gate and West Valley Drive no earlier than 2028; planning case 2029–2031
    Delivered by
    Pertinence; a state PPP is sought; a transport operator
  • Leisure

    A valley park and lakes, a sports park and, if Part B comes, golf, a resort and a water park.

    At build-out (indicative)
    295 acres of open space; 95 acres of sport; 38 acres of family park
    First step
    Valley protected from 2027; first greenway loop targeted within 2034–2038
    Delivered by
    Pertinence (parks); leisure operators
  • Faith, events & community

    Multi-faith worship sites, community halls, an event centre and retreat grounds.

    At build-out (indicative)
    16–18 worship sites; event hall for 2,000–3,000; retreat pavilion for about 5,000
    First step
    Event centre no earlier than 2032; planning case 2035–2039
    Delivered by
    Faith groups and event operators
  • End-of-life care

    Legacy Gardens: a memorial park with multi-faith sections and a separate perpetual-care trust.

    At build-out (indicative)
    18 acres reserved; first section 8–10 acres
    First step
    Interim arrangement with Iro targeted 2027; first section no earlier than 2033
    Delivered by
    Pertinence or a memorial-park operator
  • Safety

    Gated access, patrols, a CCTV control room, police posts and fire stations.

    At build-out (indicative)
    2 fire stations, 2 police posts; every home within about 5 minutes
    First step
    Security post and site office targeted within 2027
    Delivered by
    City management company; state agencies
  • Digital

    Fibre ducts in every road reserve, and a business park on firm power.

    At build-out (indicative)
    Fibre to every plot
    First step
    Ducts laid with the first road
    Delivered by
    An internet or fibre partner
  • Governance

    A city management company, a residents' association, a community trust and public reports.

    At build-out (indicative)
    Service charges and tariffs pay for operations and renewal, with audited accounts
    First step
    City management company and service-charge policy targeted within 2027
    Delivered by
    Pertinence, then residents and the trust

City-wide infrastructure

7 city-wide systems are planned to serve every use, each built one step ahead of the homes it serves and never all at once.

  • Planned

    City power

    Interim solar-hybrid supply, then mini-grids, then gas engines, batteries and a grid tie, added in modules as homes are occupied.

    At build-out
    About 36 MW peak at build-out
    First step
    Interim supply no earlier than 2030
  • Planned

    Water

    Protected boreholes inside the city, treatment, reservoirs and a piped network, staged one step ahead of occupied homes.

    At build-out
    About 13,000 m³/day at build-out
    First step
    First boreholes no earlier than 2029
  • Planned

    Sewage & waste

    Two enclosed modular sewage plants with treated-water reuse; a transfer station, recycling yard and compost.

    At build-out
    8,000 m³/day sewage · 35 t/day waste
    First step
    Sewage module 1 planning case 2038–2041
  • Planned

    Flood-resilient drainage

    Homes on the ridges, the valley kept as park and flood storage, floor levels above the modelled flood plus a margin.

    At build-out
    295 acres of valley, lakes and buffers
    First step
    Valley protected from 2027
  • Planned

    Roads & mobility

    Walkable neighbourhoods, a gateway transport hub, shuttles, and separate routes for trucks and visitors.

    At build-out
    About 26 km of spine and collector roads
    First step
    Phase 1 gate no earlier than 2028
  • Planned

    Fibre to every plot

    Ducts laid in every road reserve as it is built; an internet partner to each cluster.

    At build-out
    Fibre to every plot
    First step
    With the first road
  • Planned

    Safety & security

    Gated access, patrols, a CCTV control room, police posts and fire stations within about five minutes of every home.

    At build-out
    2 fire stations · 2 police posts
    First step
    Security post targeted within 2027

Power, water, sewage, schools and the hospital are built and run by operators and concessionaires. Qualified partners and institutions can express interest in co-developing the city.

Indicative master plan, version 1.1 (October 2026).

Phase 1 is current. Nothing is built yet.

We only show progress that is evidenced, so most of this line is still empty, on purpose.
  1. Phase 1Planning
  2. Phase 2Not started
  3. Phase 3Not started
  4. Phase 4Not started
  5. Phase 5Not started
  6. Phase 6Not started
What has been done so far

Status: Planning · as of October 2026

Phase 1 · Foundations: in planning.

No works have started on the ground. We are evidencing the title, commissioning the studies and preparing the approvals. This tracker shows progress only when it is evidenced, so most of it is still empty, on purpose.

Of the 175 milestones in the six phases, today: 1 done, 0 committed, 0 in approval, 5 to be confirmed and 169 aspirational.

Committed means funded and contracted. Nothing is Committed yet, and we will not show it until it is.

Phase 1, the basic things in order

  1. Provisional survey plan for Part A (OG/1089/2026/PROV.015)

    28 August 2026

    Done

  2. Title evidence and counsel's title opinion in the data room

    Q4 2026–Q1 2027

    To be confirmed

  3. C of O application: filing acknowledgment and reference on file

    Now

    To be confirmed

  4. Phase 1A layout-approval status

    Now

    To be confirmed

  5. Terms for the first release, with buyers' money protected in escrow

    Q4 2026–Q1 2027

    To be confirmed

  6. Part B rights confirmed in writing

    Q4 2026–2027

    To be confirmed

  7. Counsel's opinions, trustee escrow and governance adopted

    Q4 2026–Q1 2027

    Aspirational

  8. Topographic survey, block flood screening and the social baseline

    Q4 2026–Q2 2027

    Aspirational

  9. Survey registered and charted

    Within 2027; may run into 2028

    Aspirational

  10. Community Development Agreement signed

    Within 2027

    Aspirational

  11. EIA certificate

    No earlier than 2028; 2028–2029

    Aspirational

  12. Master plan and Phase 1A layout approvals

    2028–2029

    Aspirational

  13. Global C of O for Part A (the state sets the timing)

    No earlier than 2028; 2028–2030

    Aspirational

  14. Phase 1 gate and West Valley Drive (north)

    No earlier than 2028; 2029–2031

    Aspirational

  15. First serviced plots handed over

    No earlier than 2029; 2030–2032

    Aspirational

Six phases of five years.

Each phase opens when its gates are met, not when the calendar says so.
  1. Phase 1 · Now, planning2027–2031FoundationsMake the land bankable: title, trust, and one fully serviced first neighbourhood.
    Earliest window
    2027–2031
    Planning case (the window to rely on)
    2027–2032

    Evidence and perfect the title, know the ground and the people on it, win the approvals, protect the valley, and open one complete, fully serviced first neighbourhood (Phase 1A) off West Valley Drive.

    Part A · the first town

    Phase 1A: one complete neighbourhood on the highest ground of the north-west ridge, reached from the Phase 1 gate. The valley, including its head at the frontage, stays park.

    Part B · proposed

    Rights only: an option confirmed in writing. No survey spend, marketing, sale or detailed planning.

    Conservative targets · planning case at the end of 2031

    Occupied homes
    0–20
    Residents
    0–100
    On-site jobs
    50–200
    • Title evidenced, registered and charted; the EIA certificate and master-plan approval in hand
    • The first serviced neighbourhood handed over by the end of 2032 in the planning case
    • About 1.2 km of spine road, about 4 km of streets and 300–500 m³/day of water

    Stretch: About 90 homes occupied by the end of 2031 and the first mini-grid in 2032. Not a forecast.

    Title & approvals (13)
    • Provisional survey plan for Part A (OG/1089/2026/PROV.015), prepared by a SURCON-registered surveyor

      Prepared 28 August 2026; on file

      Done

    • Title evidence in a data room: the deed of assignment with its stamping and registration, the vendor's chain of title, consent status and counsel's written title opinion

      Targeted within Q4 2026–Q1 2027, before any money is taken

      To be confirmed

    • Certificate of Occupancy (C of O) application for Part A: filing acknowledgment and reference placed on file

      Filing evidence now

      To be confirmed

    • Survey lodged, registered and charted against government acquisitions, reserves and conflicting titles; root-of-title checks

      Plan number targeted within 2027; may run into 2028

      Aspirational · Pertinence

    • Topographic survey, block flood screening, hydrology, geotechnics and hydrogeology

      First blocks from Q4 2026; the rest within 2027

      Aspirational · Pertinence

    • Land-user census, social baseline and a Community Development Agreement with Iro and neighbouring communities

      Targeted within 2027

      Aspirational · With the community

    • Federal EIA, prepared to the IFC Performance Standards

      Certificate no earlier than 2028; targeted within 2028–2029

      Aspirational · Pertinence

    • Master plan approval (Ogun Ministry of Physical Planning)

      Targeted within 2028–2029, after the studies

      Aspirational · Pertinence

    • Phase 1A layout approval, with its reference published

      Status to be evidenced; if not held, targeted within 2028–2029

      To be confirmed

    • Global C of O for Part A

      No earlier than 2028; targeted within 2028–2030. The state sets the timing.

      Aspirational · Government or third party

    • Utility licences: water abstraction and the mini-grid permit (OGERC)

      Targeted within 2028–2029

      Aspirational · Pertinence

    • Title perfection for fully paid buyers: per-plot surveys, deeds and Governor's Consent in batches

      No earlier than the global C of O; first filings within 12 months of it

      Aspirational · Pertinence

    • Part B: rights confirmed in writing and an option signed

      Targeted within Q4 2026–2027

      To be confirmed

    Infrastructure (8)
    • Boundary beacons, clearing, a security post, site office and patrol track

      Targeted within 2027

      Aspirational · Pertinence

    • Valley protection: no fill, dumping or building anywhere in the valley

      From 2027, continuous

      Aspirational · Pertinence

    • Phase 1 gate and junction on the Papalanto–Sagamu Road, and about 1.2 km of West Valley Drive

      No earlier than 2028; targeted within 2029–2031

      Aspirational · Pertinence

    • Phase 1A streets (about 4 km) with drains, and 0.6 km of frontage service road

      No earlier than 2028; targeted within 2029–2031, block by block

      Aspirational · Pertinence

    • Water: 2–4 protected boreholes and an elevated tank (300–500 m³/day)

      No earlier than 2029; targeted within 2029–2031

      Aspirational · Pertinence

    • Power: an interim solar-hybrid supply sized to occupied homes, growing into a 0.5–1 MWp mini-grid

      Interim no earlier than 2030; mini-grid planning case 2033–2035

      Aspirational · Partner-led

    • Security edge: the west frontage and Phase 1A fenced (about 3 km); solar street lighting on the spine

      Targeted within 2029–2031

      Aspirational · Pertinence

    • Sanitation: approved sealed septic tanks emptied by licensed tankers, until the first sewage plant

      From the first occupation

      Aspirational · Pertinence

    Releases (4)
    • The first serviced neighbourhood (Phase 1A). Plots are allocated only on the approved layout; release terms and money protection are being confirmed

      Allocation only after the Phase 1A layout approval: planning case 2029–2030

      To be confirmed

    • Serviced handover, block by block: road access, drains and a water point, then power when the interim supply opens, verified by an independent quantity surveyor

      No earlier than 2029; targeted within 2030–2032

      Aspirational · Pertinence

    • First frontage commercial plots, on their own service road

      No earlier than 2029; targeted within 2031–2034

      Aspirational · Pertinence

    • First Ridge Works plots, sold with build-start covenants; an anchor parcel held for an anchor

      No earlier than 2030; targeted within 2032–2035

      Aspirational · Partner-led

    Community & services (3)
    • Community liaison office and benefit plan: local hiring, apprenticeships and scholarships

      Targeted within 2027–2028

      Aspirational · With the community

    • First-aid post and an ambulance arrangement to the nearest hospital

      From the first works

      Aspirational · Pertinence

    • A neighbourhood park and the first section of the valley greenway beside Phase 1A

      Targeted within 2030–2032

      Aspirational · Pertinence

    Partner projects (6)
    • Ofada heritage rice paddies and a tree nursery: the first visible activity on site

      Pilot targeted within 2027–2029, once hydrology confirms the paddy areas

      Aspirational · Partner-led

    • A power partner for the interim supply and the first mini-grid

      Agreement targeted within 2027–2028

      Aspirational · Partner-led

    • Memoranda of understanding (not buildings yet) with a hospital operator, a school operator, an event operator and a water concessionaire

      Targeted within 2027–2029

      Aspirational · Partner-led

    • A Ridge Works anchor occupier (agro-processing or light manufacturing)

      Targeted within 2028–2031

      Aspirational · Partner-led

    • A show village of model homes in Phase 1A

      No earlier than 2030; targeted within 2031–2032

      Aspirational · Partner-led

    • Fuel, CNG and EV charging at the north-east junction

      No earlier than 2030; targeted within 2031–2034

      Aspirational · Partner-led

    Gates to open Phase 2 · all must be true

    • The global C of O for Part A granted, with any land under acquisition held back on a documented route.
    • The EIA certificate held; the master plan and the Phase 2 layout approved.
    • The first neighbourhood serviced and handed over, verified by an independent quantity surveyor, with no buyer past their contracted handover window.
    • Phase 2 passes its funding test: an independent cost plan shows its committed sources cover its costs, with buyers' receipts held in escrow.
    • A power partner contracted and the OGERC licensing route confirmed.
    • The city management company operating, with its service-charge accounts published.
    • The host-community agreement in force and no unresolved claim on Phase 2 land.
  2. Phase 22032–2036First LightMake it liveable: serviced releases, the first schools, city utilities as demand arrives, and the town centre.
    Earliest window
    2032–2036
    Planning case (the window to rely on)
    Opens 2032–2033; runs to 2039–2041

    Serviced releases continue block by block. Valley Boulevard and Ridge Central begin when their anchors are in sight. Utilities, schools and a health centre open as occupied homes reach their triggers. Operators may choose to come earlier.

    Part A · the first town

    Phase 1B, Ridge Heights, the west neighbourhood centre, the main gateway, Valley Boulevard to Ridge Central and the health campus, staff homes and terraces, the event centre and the utilities campus.

    Part B · proposed

    If an option is in force: survey, charting, root of title and the C of O application. Nothing is marketed or sold.

    Conservative targets · planning case at the end of 2036

    Occupied homes
    250–500
    Residents
    900–1,900
    On-site jobs
    200–750
    • Phase 1B handed over; Ridge Heights being serviced
    • About 1,000 m³/day of water and a mini-grid of about 1 MWp; sealed septic tanks still in use
    • The first primary school and Ridge Central stage 1 under way with operators

    Stretch: About 1,300 homes occupied by the end of 2036, with power module 1 and the health centre in 2036. Not a forecast.

    Title & approvals (6)
    • Governor's Consent for fully paid plots, in batches, so that mortgages can be registered

      Continuous from the C of O; 2032–2038

      Aspirational · Pertinence

    • Phase 2 layout approvals: Phase 1B, Ridge Heights, the neighbourhood centres and Ridge Central

      Targeted within 2031–2033

      Aspirational · Pertinence

    • Power licensing for city power module 1 (OGERC) and a gas-supply agreement (NMDPRA)

      Targeted within 2036–2039

      Aspirational · Partner-led

    • Legacy Gardens approval by Obafemi-Owode Local Government at the chosen site

      Targeted within 2032–2035

      Aspirational · Government or third party

    • The first environmental audit and the first five-year master-plan review, adopted publicly

      Targeted within 2032–2034

      Aspirational · Pertinence

    • Part B, only under a signed option: survey, charting, root of title and the C of O application

      No earlier than 2032; targeted within 2032–2036

      Aspirational · Pertinence

    Infrastructure (8)
    • West Valley Drive south, the first collector roads and local streets, block by block

      No earlier than 2032; targeted within 2033–2038

      Aspirational · Pertinence

    • Valley Boulevard section 1 (about 1.8 km) to Ridge Central and the health campus

      No earlier than 2034; targeted within 2035–2038

      Aspirational · Pertinence

    • The main gateway and junction east of the valley head

      No earlier than 2033; targeted within 2035–2038

      Aspirational · Pertinence

    • The full Part A perimeter and a CCTV control room

      Targeted within 2033–2036

      Aspirational · Pertinence

    • Water stage 1: treatment, storage and a piped network (1,000–1,500 m³/day)

      Targeted within 2034–2038, one step ahead of occupied homes

      Aspirational · Partner-led

    • City power module 1 (about 3–5 MW firm)

      No earlier than 2033; planning case 2039–2041, at about 1,000 occupied homes

      Aspirational · Partner-led

    • Sewage module 1 (500 m³/day)

      No earlier than 2032; planning case 2038–2041, at about 800 homes in one catchment

      Aspirational · Partner-led

    • The valley greenway's first loop (2–4 km)

      Targeted within 2034–2038

      Aspirational · Pertinence

    Releases (5)
    • Later serviced releases: Phase 1B (Ridge Courts West, Ridge Gardens near the west centre, the lakeside Homecoming Enclave)

      Handover planning case 2032–2035

      Aspirational · Pertinence

    • Ridge Heights, on the south-west high ground

      Handover no earlier than 2032; planning case 2034–2037

      Aspirational · Pertinence

    • Land for partner-built terraces and staff and affordable homes

      Released no earlier than 2032; first completions planning case 2034–2036

      Aspirational · Partner-led

    • Ridge Central parcels around the developer-held core

      No earlier than 2034; targeted within 2036–2039

      Aspirational · Pertinence

    • Sites leased to operators: the health campus, schools and the event centre; worship sites under a published policy

      As each operator signs; 2034–2039

      Aspirational · Partner-led

    Community & services (5)
    • First nursery and primary school

      No earlier than 2032; planning case 2037–2040, at about 600 occupied homes

      Aspirational · Partner-led

    • 24-hour health centre with maternity

      No earlier than 2032; planning case 2039–2041, at about 1,000 occupied homes

      Aspirational · Partner-led

    • Community hall, the first worship sites and the community sports park, stage 1

      Targeted within 2035–2039

      Aspirational · Pertinence

    • Police post and fire station 1

      Targeted within 2035–2039

      Aspirational · Government or third party

    • Legacy Gardens, first section (multi-faith, including same-day burial)

      No earlier than 2033; targeted within 2034–2037

      Aspirational · Pertinence

    Partner projects (6)
    • Gateway event centre (a hall for about 2,000–3,000 guests)

      No earlier than 2032; targeted within 2035–2039

      Aspirational · Partner-led

    • Ridge Central stage 1: market, supermarket, banks, offices and the civic plaza

      No earlier than 2034; targeted within 2036–2039

      Aspirational · Partner-led

    • Water and sewage concession for Part A

      Contract targeted within 2033–2036

      Aspirational · Partner-led

    • Gateway transport hub and scheduled shuttles

      Targeted within 2036–2039

      Aspirational · Partner-led

    • Partner-built terraces and staff homes

      2033–2040

      Aspirational · Partner-led

    • A filling station on the east road for trucks

      2034–2039

      Aspirational · Partner-led

    Gates to open Phase 3 · all must be true

    • Phase 2 trunk works at least 80% complete, verified by the independent quantity surveyor.
    • Water and power operating, with tariffs or service charges published and audited; sewage module 1 operating or contracted.
    • About 1,000 occupied homes, or equivalent anchor demand.
    • At least two anchors operating: the first primary school, and the health centre or Ridge Central stage 1.
    • The Phase 3 layout approved and Phase 3's funding test passed.
    • A residents' association constituted and the first environmental audit passed.
  3. Phase 32037–2041The Complete TownMake it complete: all of Part A's trunk infrastructure.
    Earliest window
    2037–2041
    Planning case (the window to rely on)
    Opens 2039–2041; Part A trunk complete 2044–2047

    All of Part A's main roads, drains, power ring, water mains and sewers are completed: no earlier than the end of 2041, and in the planning case in 2044–2047. Part A becomes a working town of its own, whether or not Part B follows.

    Part A · the first town

    Completion: Valley Boulevard section 2, Ridge Gardens and Courts East, apartments, the Golden Years cluster, the gateway hotel, Tech Valley, the Agri-Hub core, the secondary school, hospital stage 1, Legacy Gardens and the valley park.

    Part B · proposed

    C of O, EIA, master plan and first layout approval; the leisure parkway agreed with the state. No Part B parcel is serviced before every approval is in hand.

    Conservative targets · planning case at the end of 2041

    Occupied homes
    1,250–1,700
    Residents
    4,700–6,500
    On-site jobs
    1,100–2,550
    • About 5 MW of firm power, 3,000 m³/day of water and 2,000 m³/day of sewage treatment
    • Primary school, health centre and Ridge Central stage 1 operating
    • Part A trunk completion targeted for 2044–2047

    Stretch: About 2,850 homes occupied by the end of 2041 and Part A's trunk complete by end-2041. Not a forecast.

    Title & approvals (4)
    • Part B global C of O (only if Part B is secured)

      No earlier than 2034; targeted within 2035–2039. The state sets the timing.

      Aspirational · Government or third party

    • Part B EIA, master plan and first layout approval; the leisure parkway agreed with Ogun State and the LGA

      Targeted within 2039–2044

      Aspirational · Pertinence

    • Power licence upgrade (OGERC) and a grid-connection application

      Targeted within 2041–2045

      Aspirational · Partner-led

    • Buyers' title perfection substantially complete for the first releases

      Targeted by 2043

      Aspirational · Pertinence

    Infrastructure (6)
    • All of Part A's trunk: Valley Boulevard section 2, collectors, storm drainage, the 33 kV ring, water mains and sewers

      No earlier than end-2041; planning case 2044–2047

      Aspirational · Pertinence

    • Cross-valley links, built as bridges or open causeways that let floodwater pass

      Targeted within 2041–2045

      Aspirational · Pertinence

    • Power module 2 and the Part A solar plant complete

      Targeted within 2041–2046

      Aspirational · Partner-led

    • Water stage 2, and sewage module 2 with treated water reused on parks and farms

      Targeted within 2040–2046

      Aspirational · Partner-led

    • The valley park complete, with the greenway loop around Part A

      Targeted within 2040–2046

      Aspirational · Pertinence

    • Recycling and compost yards; fire station 2

      2040–2046

      Aspirational · Partner-led

    Releases (4)
    • Ridge Gardens East and Ridge Courts East, sold as serviced releases

      Handover targeted within 2038–2042

      Aspirational · Pertinence

    • Apartments near Ridge Central and the Golden Years cluster beside the health campus

      Targeted within 2041–2046

      Aspirational · Partner-led

    • Sites for the gateway hotel and Ridge Tech Valley

      No earlier than 2037; targeted within 2040–2044

      Aspirational · Partner-led

    • The Agri-Hub core and the rest of the Part A paddies

      2039–2045

      Aspirational · Partner-led

    Community & services (4)
    • Hospital stage 1 (about 50 beds, with maternity and children's care)

      No earlier than 2035; planning case 2043–2046, at about 2,000 occupied homes

      Aspirational · Partner-led

    • First secondary school, then more primary schools as enrolment grows

      No earlier than 2034; planning case 2041–2044, at about 1,500 occupied homes

      Aspirational · Partner-led

    • Library and community centre in Ridge Central; a clinic in each neighbourhood centre

      2040–2046

      Aspirational · Pertinence

    • A second police post and fire station

      2041–2046

      Aspirational · Government or third party

    Partner projects (4)
    • Gateway hotel and serviced apartments (about 100–120 keys)

      No earlier than 2037; targeted within 2040–2044, once event demand is proven

      Aspirational · Partner-led

    • Ridge Tech Valley: offices, co-working and BPO on firm power and fibre

      No earlier than 2037; targeted within 2041–2045

      Aspirational · Partner-led

    • Agri-Hub stage 2: greenhouses, aquaculture, a training centre and the farmers' market

      2039–2045

      Aspirational · Partner-led

    • Hospital stage 1, with development-finance support where it qualifies

      Planning case 2043–2046

      Aspirational · Partner-led

    Gates to open Phase 4 · all must be true

    • Part A trunk infrastructure at least 80% complete, on a funded path to completion and verified by the independent quantity surveyor.
    • Part B's C of O, EIA and first layout approval in hand before any Part B sale or servicing.
    • The leisure parkway agreed with Ogun State and the LGA.
    • At least one destination operator signed, with its own financing, before land is serviced for it.
    • At least 5 MW of firm power and 3,000 m³/day of water operating, with three years of audited accounts.
    • Phase 4's funding test passed.
  4. Phase 42042–2046The Destination CityMake it a destination: Part B and the leisure parkway.
    Earliest window
    2042–2046
    Planning case (the window to rely on)
    Opens 2044–2047; first destination operator trading 2046–2050

    With Part B titled and operators signed, the resort, golf course, retreat and convention grounds, amusement and water park, sports complex and a tertiary campus open on their own leisure parkway. None opens before 2042; in the planning case the first destination operator trades in 2046–2050.

    Part A · the first town

    Infill, homes near Ridge Central, and the hospital's growth.

    Part B · proposed

    The leisure parkway, Part B's first trunk works, the destination uses, the first Part B neighbourhoods, the district centre and Part B utilities.

    Conservative targets · planning case at the end of 2046

    Occupied homes
    2,300–2,700
    Residents
    8,700–10,200
    On-site jobs
    2,050–4,050
    • About 12 MW of firm power, 5,000 m³/day of water and 3,000 m³/day of sewage treatment
    • The first destination operator trading in 2046–2050 in the planning case

    Stretch: About 4,000 homes occupied by the end of 2046 and destination uses from 2042–2044. Not a forecast.

    Title & approvals (3)
    • Part B layout approvals stage by stage; operators' permits; event-day traffic plans agreed with the state and LGA

      2044–2050

      Aspirational · Pertinence

    • Water licence for Part B and the discharge permit for sewage plant B

      Targeted within 2045–2050

      Aspirational · Pertinence

    • Master plan review 3, adopted publicly

      2042–2043

      Aspirational · Pertinence

    Infrastructure (4)
    • The leisure parkway: the east road upgraded and extended, with a visitor park-and-ride

      No earlier than 2042; targeted within 2045–2049

      Aspirational · Government or third party

    • Part B collectors and local streets for the first neighbourhoods

      2045–2051

      Aspirational · Pertinence

    • Part B utilities: solar plant B, substation, water works and sewage plant

      Targeted within 2046–2051

      Aspirational · Partner-led

    • Ridge Lake as flood storage; the Part B perimeter and gates

      2045–2051

      Aspirational · Pertinence

    Releases (3)
    • Destination sites on long lease or joint venture, each only after its operator signs

      No earlier than 2042; targeted within 2045–2050

      Aspirational · Partner-led

    • Part B neighbourhoods 1 and 2

      No earlier than 2042; targeted within 2046–2051

      Aspirational · Pertinence

    • Part B district centre and health satellite

      Targeted within 2047–2051

      Aspirational · Partner-led

    Community & services (3)
    • Hospital toward about 100, then 150 beds; the Part B health satellite

      No earlier than 2043; targeted within 2047–2052

      Aspirational · Partner-led

    • Part B schools, and a tertiary or vocational campus

      No earlier than 2042; targeted within 2047–2052

      Aspirational · Partner-led

    • Fire and police cover for Part B

      2047–2052

      Aspirational · Government or third party

    Partner projects (5)
    • Lakeside wellness resort and spa (about 100–150 keys)

      No earlier than 2042; targeted within 2046–2050

      Aspirational · Partner-led

    • 9-hole golf course, driving range and academy

      No earlier than 2042; targeted within 2046–2050

      Aspirational · Partner-led

    • Retreat and convention grounds with a convention hotel and lodges

      No earlier than 2042; targeted within 2046–2050

      Aspirational · Partner-led

    • Family amusement and water park

      No earlier than 2042; targeted within 2046–2050

      Aspirational · Partner-led

    • Regional sports complex and academy

      No earlier than 2043; targeted within 2047–2051

      Aspirational · Partner-led

    Gates to open Phase 5 · all must be true

    • The leisure parkway open and at least two destination operators trading.
    • An event-day traffic management plan approved and tested.
    • Part B trunk infrastructure at least 50% complete, verified by the independent quantity surveyor.
    • Master plan review 3 adopted and Phase 5's funding test passed.
  5. Phase 52047–2051MaturityMake it mature: full systems and the golden years.
    Earliest window
    2047–2051
    Planning case (the window to rely on)
    Opens 2050–2053; Part B trunk complete 2056–2060

    Part B's trunk infrastructure is completed (no earlier than the end of 2051; planning case 2056–2060), and city systems grow toward build-out capacity, sized for a design population of 35,000.

    Part A · the first town

    Renewal and, where demand supports it, more homes near the centres.

    Part B · proposed

    Trunk completion, apartments, Golden Years Village B, Tech Valley B and agro-processing.

    Conservative targets · planning case at the end of 2051

    Occupied homes
    2,900–3,400
    Residents
    11,100–12,900
    On-site jobs
    2,600–5,100
    • About 12 MW of firm power, 8,000 m³/day of water and 4,000 m³/day of sewage treatment
    • Part B trunk under way; completion targeted for 2056–2060

    Stretch: About 5,850 homes occupied by the end of 2051. Not a forecast.

    Title & approvals (2)
    • Master plan review 4 and licence renewals

      2047–2048

      Aspirational · Pertinence

    • A Legacy Gardens extension in Part B, only if demand needs it, under the same siting tests

      No earlier than 2047

      Aspirational · Government or third party

    Infrastructure (3)
    • Part B trunk infrastructure complete: spine, collectors, storm drainage and sewers

      No earlier than end-2051; planning case 2056–2060

      Aspirational · Pertinence

    • Power, water and sewage grow toward build-out; the first battery replacement cycle

      2050–2056

      Aspirational · Partner-led

    • Waste transfer at full capacity

      2050–2056

      Aspirational · Partner-led

    Releases (2)
    • Apartments B, Golden Years Village B, Tech Valley B and the agro-processing cluster

      No earlier than 2047; targeted within 2050–2056

      Aspirational · Partner-led

    • The remaining Part B neighbourhoods

      2050–2056

      Aspirational · Pertinence

    Community & services (3)
    • Hospital at about 150 beds if demand supports it; six primary health centres city-wide

      2050–2056

      Aspirational · Partner-led

    • Schools toward 7–8 primary and 4–5 secondary

      2050–2056

      Aspirational · Partner-led

    • Assisted living and day care for older residents

      2050–2056

      Aspirational · Partner-led

    Partner projects (2)
    • Golden Years Village B: independent and assisted living

      No earlier than 2047; targeted within 2050–2056

      Aspirational · Partner-led

    • Ridge Tech Valley B and the agro-processing cluster

      No earlier than 2047; targeted within 2050–2056

      Aspirational · Partner-led

    Gates to open Phase 6 · all must be true

    • Part B trunk infrastructure handed over to the city management company and verified by the independent quantity surveyor.
    • Master plan review 4 adopted.
    • The Ridge City Community Trust endowed from land proceeds; the memorial park's perpetual-care trust audited and separate.
    • An asset-renewal plan funded from service charges and tariffs.
  6. Phase 62052–2056LegacyMake it last: build-out, renewal and stewardship.
    Earliest window
    2052–2056
    Planning case (the window to rely on)
    Opens 2055–2060; build-out runs beyond 2056

    Infill and the final releases, repowering of the first solar plants, and the hand-over of the valley, the greenways and the community assets to a community trust. Build-out (about 7,700 homes) runs beyond 2056 in the planning case.

    Part A · the first town

    Renewal and infill near the centres if demand supports it.

    Part B · proposed

    The final neighbourhoods, and a public decision on the strategic reserve.

    Conservative targets · planning case at the end of 2056

    Occupied homes
    3,950–4,600
    Residents
    15,000–17,500
    On-site jobs
    3,550–6,900
    • About 20 MW of firm power, 10,000 m³/day of water and 5,000 m³/day of sewage treatment
    • Community assets handed to the trust; build-out continues beyond 2056

    Stretch: About 7,100 homes occupied by the end of 2056. Not a forecast.

    Title & approvals (2)
    • Master plan review 5 and the strategic-reserve decision

      No earlier than 2052

      Aspirational · Pertinence

    • The Ridge City Community Trust registered and funded

      Targeted within 2052–2056

      Aspirational · With the community

    Infrastructure (4)
    • Local streets complete

      2055–2060

      Aspirational · Pertinence

    • Power at build-out, with the first-generation solar repowered

      2055–2060

      Aspirational · Partner-led

    • Water and sewage at build-out

      2055–2060

      Aspirational · Partner-led

    • Road resurfacing and plant renewal paid from the renewal reserves

      2055–2060

      Aspirational · Pertinence

    Releases (2)
    • The remaining infill plots and parcels

      2055–2060

      Aspirational · Pertinence

    • The strategic reserve: a second golf nine, a campus expansion, a transit link or a data centre, decided publicly

      No earlier than 2052

      Aspirational · Pertinence

    Community & services (1)
    • Full provision for the design population: schools, up to about 150 hospital beds, six health centres and two fire stations

      At build-out; beyond 2056 in the planning case

      Aspirational · Partner-led

    Partner projects (2)
    • Apartments near Ridge Central and the Part B district centre, if demand supports them

      No earlier than 2052

      Aspirational · Partner-led

    • A strategic-reserve project chosen at review

      No earlier than 2052

      Aspirational · Partner-led

    Hand-over conditions · all must be true

    • The community trust endowed and governed, with residents represented.
    • The perpetual-care trust separate and audited.
    • Renewal reserves funded from service charges and tariffs.
    • Residents on the city management company's board.

Indicative, subject to approvals. Every date is a target window, never a promise.

What the status labels mean
Done
Completed, with the evidence on file.
Committed
Funded and contracted. Nothing carries this label yet.
In approval
An application is lodged and its reference is on file; a public body controls the outcome and timing.
To be confirmed
The facts must be evidenced in writing before the item is relied on.
Aspirational
Planned, but not yet funded and contracted.
How we set target windows

Every comparable new city in Africa delivered more slowly than first announced. So every date here is a target window with its conditions, set from a conservative model of how fast owners actually build, and never a promise.

  • No earlier than

    The earliest year a milestone could happen. A phase cannot open before its 5-year window.

  • Planning case

    The conservative window we plan and fund against, derived from the occupancy model and the gates. This is the one to rely on.

  • Stretch

    What could happen if approvals, sales and partners move faster. Shown for completeness; not a forecast.

The rules this plan follows

  • A phase opens when its gates are met, including a funding test, not when the calendar says so.
  • Facilities open on evidence: each has a demand trigger (occupied homes or an operator's own case), plus about a year to build.
  • Committed means funded and contracted. Anything that needs an operator, utility or financier is Aspirational until it signs.
  • We sell only what can be serviced, and plots are allocated only on an approved layout.
  • Buyers' money is held in escrow and released against certified works (proposed, to be adopted before any money is taken).
  • If a gate slips, the next phase slips, and we say so publicly within 14 days, with the reason and a new window.
  • Unbuilt infrastructure is never priced into a plot.

Our planning case assumes owner-builders build slowly: about a quarter of a year's handed-over plots occupied four years later, and about half after nine. On that basis the city reaches about 1,000 occupied homes in 2039–2041, and every facility that waits for that threshold is placed there, not earlier.

Facilities open on evidence, not on hope

Demand triggers: when each facility opens, the earliest year and the planning-case window
FacilityOpens whenNo earlier thanPlanning case
First solar-hybrid mini-grid (0.5–1 MWp)About 100 occupied homes, or an industrial anchor20302033–2035
First nursery and primary schoolAbout 600 occupied homes, or an operator's own enrolment case20322037–2040
Sewage module 1 (500 m³/day)About 800 occupied homes in one catchment20322038–2041
24-hour health centre with maternityAbout 1,000 occupied homes, or an operator's own case20322039–2041
City power module 1 (about 3 MW firm)About 1,000 occupied homes, or an anchor needing more than 1 MW20332039–2041
First secondary schoolAbout 1,500 occupied homes, or an operator's own case20342041–2044
Hospital stage 1 (about 50 beds)About 2,000 occupied homes, or a wider-catchment case20352043–2046
Gateway hotelEvent bookings and corridor demand proven by the operator20372040–2044
Resort, golf, water park, retreat groundsAn operator signed with its own financing; Part B titled20422046–2050

Each window includes about a year to build after the trigger is met. Operators are welcome to come earlier on their own business case; the plan never assumes it.

What comparable new cities teach

  • Alaro City, Lagos

    About seven years from conception to groundbreaking, even with the state as a partner. Plots were sold after the C of O and master plan.

  • Tatu City, Kenya

    First homes launched in 2015 and phased over 20 years; about ten years from launch to a functioning town (company-reported).

  • Lekki Free Zone, Lagos

    Incorporated in 2006; its big anchors arrived about 17 years later. Anchor-driven cities have long gestation.

Sources

Cited for their timelines only. The Ridge City is independent of these projects and implies no endorsement.

Title and approvals, in order

Before a plot can be sold under a binding contract, the land needs evidenced title, a registered and charted survey, a counted and consulted community, flood-screened blocks and the layout approval. Before it can be handed over, it needs the EIA and the works. Most of these steps are in the hands of state and federal agencies.

Title status today

Deed of assignment in place; provisional survey plan (OG/1089/2026/PROV.015) for Part A completed by a SURCON-registered surveyor; Certificate of Occupancy (C of O) application in process.

  1. Step 1: Title evidence and counsel's opinions

    Counsel; Ogun Lands Registry

    The deed of assignment (parties, date, stamping, registration), the vendor's chain of title, consent status and a written title opinion, placed in a data room.

    Q4 2026–Q1 2027, before any money is taken

    To be confirmed

  2. Step 2: Register and chart the survey

    Ogun Surveyor-General; Bureau of Lands

    Lodge the provisional plan, obtain a registered plan number and chart it against acquisitions, reserves and conflicting titles.

    3–9 months; targeted within 2027

    Aspirational

  3. Step 3: Root of title and acquisition check

    Bureau of Lands; Land Use Act

    Confirm the land is not under government acquisition; if any is, hold it back and follow an excision or ratification route.

    6–18 months, in parallel

    Aspirational

  4. Step 4: Know the ground and the people on it

    Within the EIA scope

    Topographic survey, block flood screening, hydrology, hydrogeology and a land-user census and social baseline, before any binding sale.

    First blocks from Q4 2026; full studies within 2027

    Aspirational

  5. Step 5: Federal EIA

    Federal Ministry of Environment (EIA Act)

    Scoping, baseline studies, a 21-day public display and hearing, then the certificate; prepared to the IFC Performance Standards.

    12–24 months; certificate no earlier than 2028, targeted 2028–2029

    Aspirational

  6. Step 6: Master plan and Phase 1A layout approval

    Ogun Ministry of Physical Planning (2025 regulations)

    Approve the indicative master plan and a phased layout. No plot is allocated or pegged before the layout approval.

    6–18 months; targeted 2028–2029

    To be confirmed

  7. Step 7: Global Certificate of Occupancy

    Ogun Bureau of Lands (OLARMS)

    The C of O for Part A follows survey registration and a clean root of title. The state controls the timing.

    No earlier than 2028; targeted 2028–2030

    Aspirational

  8. Step 8: Governor's Consent for buyers

    Land Use Act s.22

    Per-plot surveys, deeds and consent in batches, once the C of O exists. Mortgages can be registered only after consent.

    6–12 months per batch, after the C of O

    Aspirational

  9. Step 9: Utility and operator licences

    OGERC, NMDPRA, NIWRMC, Ministry of Health, Local Government

    Power, gas, water abstraction, hospital registration, filling stations and the memorial park, each before its facility opens.

    As each facility approaches its trigger

    Aspirational

  10. Step 10: All major infrastructure

    Pertinence, concessionaires and the state

    All of Part A's main roads, drains, power ring, water mains and sewers.

    No earlier than end-2041; planning case 2044–2047

    Aspirational

When will all major infrastructure be built?

Part A
No earlier than end-2041; planning case 2044–2047
Part B (only if secured and titled)
No earlier than end-2051; planning case 2056–2060
Build-out (about 7,700 homes)
Beyond 2056 in the planning case

These are targets. The schedule is driven by approvals, sales, partners and funding tests; most title steps are controlled by state and federal agencies, and we never imply a C of O date.

Infrastructure by phase

Cumulative at the end of each phase’s earliest window. The large figure is the planning case; the small one in brackets is the stretch case, which is not a forecast. Utilities are sized to occupied homes, never to plots sold.

Infrastructure by phase, cumulative at the end of each phase’s earliest window: planning case, with the stretch case in brackets
System (cumulative)P1End-2031P2End-2036P3End-2041P4End-2046P5End-2051P6End-2056
Spine roads (km)About 12.5 km at build-out (West Valley Drive, Valley Boulevard, leisure parkway)12(4)4(6)6(10)8(13)10(13)
Other collector roads (km)About 13.5 km at build-out00(2)2(5)5(7)7(12)12(14)
Local streets (km)About 53 km at build-out, the rest inside partner parcels5(8)11(13)17(22)22(28)28(40)40(47)
Valley greenway (km)About 12 km at build-out0(1)33(8)8(10)10(12)12
Firm power (MW)Module 1 at about 1,000 occupied homes; about 36 MW peak at build-out00(8)5(12)12(20)12(25)20(35)
Solar (MWp)Ground-mounted, rooftop and a floating option0(1)1(8)8(9)9(18)17(20)18(21)
Water production (m³/day)One step ahead of occupied homes; 13,000 m³/day at build-out3001,000(3,000)3,000(8,000)5,000(10,000)8,000(13,000)10,000(13,000)
Sewage treatment (m³/day)Sealed septic tanks until module 1; 8,000 m³/day at build-out00(2,000)2,000(4,000)3,000(5,000)4,000(8,000)5,000(8,000)
Occupied homes (homes)The occupancy model; about 7,700 homes at build-out0(90)250(1,300)1,250(2,850)2,300(4,000)2,900(5,850)3,950(7,100)
Risks we manage

The risks that matter most here, and how the plan is built to absorb them.

  • Title and approvals take longer than the windows.

    Conservative windows taken from comparable cities; works start on gates, not dates; a title update every 30 days until the C of O is granted.

  • Title evidence turns out weaker than stated, or charting finds land under acquisition.

    Evidence before any money is taken; the exact title wording everywhere; charting before any binding contract; affected land held back from sale.

  • The valley is wetter or larger than the desk study suggests.

    Hydrology first; homes on flood-screened high ground only; floor levels above the modelled flood; a relocation-or-refund clause in every contract.

  • Buyers wait longer than their contracts say.

    We sell only what can be serviced; handover windows and long-stop dates in contracts; no allocation before the layout approval.

  • Anchors such as a hospital or schools do not come when planned.

    Operators courted from 2027; published demand triggers; long leases on anchor terms; smaller interim facilities first.

  • Land sales alone do not pay for all of the infrastructure.

    We say so openly. Each phase must pass an independent funding test before it opens; utilities are concession-financed; partners are sought for the rest.

  • Gas supply or power licensing is delayed.

    Solar and batteries first, trucked gas as a bridge, the OGERC route confirmed early, and the grid treated as an upside, never a dependency.

  • People farm, live on or hold sacred sites on the land; community disputes.

    A land-user census now, a livelihood-restoration framework, a heritage protocol and a Community Development Agreement before works.

  • Part B is not secured, not next to Part A, or priced up by hold-outs.

    Part A is planned as a complete town on its own; Part B is never marketed or sold before it is titled.

  • Naira cost inflation.

    A 30–50% contingency in the cost plan, imported equipment carried by partners, and an annual re-baseline of costs.

Artist's impression: a valley lake with a timber boardwalk, tall grasses and green hills

Build it with us

A city is built by many hands.

Come and walk the land. Qualified partners and institutions can also express interest in co-developing the city.